(Feb. 10, 2014, 4:15 p.m., updated Feb. 11, 11:55 a.m.) -- LBREPORT.com has learned that the City of Long Beach was advised by a detailed report over eight years ago to begin taking measures to seismically retrofit Long Beach City Hall. The record indicates that city staff began exploring retrofit options in the final months of the O'Neill administration but effectively shifted to favoring a full Civic Center rebuild under Mayor Foster and his Council majorities.
LBREPORT.com has obtained a copy of a report, dated Sept. 3, 2005, provided to the City of Long Beach, titled "Long Beach City Hall Life Safety Performance Evaluation, Based on FEMA 310 Tier 2," (hereafter "Report")performed by 3D International of Los Angeles. LBREPORT.com obtained the document from the City within the past few days following a request initially made in October 2013.
The report states in pertinent part:
Alternatively, the conceptual retrofit measures suggested here could be further developed into detailed retrofit design and implemented...
Although, there are no mandatory retrofit requirements from the building jurisdiction that we are aware of, it is our professional opinion that the building should be retrofitted to alleviate life-save concerns during a major seismic event. [Source: Report, Executive Summary, p. 4.] The report included "Recommended Conceptual Upgrades" including six specific measures to mitigate seismic deficiencies, and also provided sketches of the retrofits.
At a Feb. 1, 2014 public meeting, city management acknowledged that it hasn't issued a Request for Proposals seeking bids/proposals from firms that actually do retrofitting and stated its reasons for this [see transcript below]
Following receipt of the Sept. 2005 report, city management agendized an item for the Feb. 21, 2006 Council meeting, recommending development of mitigation designs, evaluation of alternatives and financing strategies, seeking $80,000 for the task (approved by the Council. In an accompanying Power Point Presentation, then-Public Works Director Christine Andersen stated: "While the probability of a sufficiently significant seismic event is still very low -- it is prudent to take next steps to evaluate retrofit strategies." Mayor Foster took office in mid-July 2006, and on May 15, 2007 Public Works Director Andersen (who after being reassigned under new City Manager Pat West to run LB Airport left LB to become Santa Barbara's Public Works Director) presented a Power Point that indicated an outside firm had used three consultants (one for cost estimating) which estimated a structural update (without building code updates) would cost $78 million and with building code updates would cost $151 million (both estimates including $12.8 million to relocate during construction.) The May 15, 2007 Power Point included a slide stating: "Given the current age of City Hall and likely code updates requirements, minimum costs for rehabilitation of City Hall are more reasonably tied to full Renovation. A new structure better able to serve well into the future becomes appropriate to consider." It mentioned a meeting coming up in two weeks (May 29, 2007) at which an advisory "Downtown Visioning" committee would suggest downtown area changes including at the Civic Center. City management's May 15, 2007 Power Point recommended the following: "Include consideration of a new City Hall to address seismic deficiencies. Approve Main Library Roof project to allow full utilization of structure during planning permitting, design and construction period for New Civic Center Complex." The presentation didn't include a financing plan; a "public private partnership" wasn't mentioned. In August 2008, Mayor Foster and city management and a Council majority (8-1, Schipske dissenting) supported placing a measure on the Nov. 2008 ballot proposing to levy a parcel tax (Measure I) on LB property owners to repair/replace items in categories that included "...fire and police stations and other public safety facilities, parks and recreation and community facilities...libraries and health facilities." The measure's text and ballot arguments didn't mention retrofitting City Hall or a Civic Center rebuild. The measure failed to receive the 2/3 voter approval level required for its passage. On June 21, 2011, an item appeared as a 3:30 p.m. Study Session (no action) item "regardind the Civic Center." City staff presented the Power Point at this site.. There was no accompanying city management memo. LBREPORT.com reported what took place (text below): (June 26, 2011) -- As reported earlier this week on LBReport.com's front page, the City Council held a June 21 study session (no action taken) regarding the Civic Center and a possible new City Hall. On February 12, 2013, the Civic Center project reappeared on the City Council's agenda. The agenda item summarized the September 2005 report's retrofit recommendations in four bullet points, then estimated the retrofit costs in 2013 dollars at $170 million. It also asserted the view that LB's current City Hall is "functionally obsolete." At the Feb. 13 Council meeting, Councilmembers directed staff to invite a Request for Qualifications from firms that might wish to respond to a Request for Proposals to build/finance/operate a new LB City Center...and the Council asked city staff to update the 2005 seismic report with either a peer review or a new study. On Oct. 22, 2013, city staff sought Council approval to prepare a Request for Proposals for a new Civic Center. City staff's agendizing memo stated that it had commissioned a new study which "concluded that action must be taken immediately to either retrofit or construct a new facility." [emphasis added.] Staff's memo then went on to list cost figures with no data sources cited: [City staff Oct. 22, 2013 memo by Mike Conway, Dir. of Business & Property Development and Ara Maloyan, Acting Dir of Public Works, initialed as approved City Mgr. Pat West] Given the original study was performed in 2005 and newer established criteria that assess building performance during a seismic event now exist, staff commissioned a new seismic report. The conclusions confirm the precarious stability of City Hall and the extensive renovations necessary to retrofit the building to perform in a seismic event. The study concluded that action must be taken immediately to either retrofit or construct a new facility. Staff will be presenting more details and information related to the new seismic study at the City Council meeting. On December 3, 2013, the City Council voted 7-1 (Schipske dissenting, Lowenthal absent) to approve entering into a contract with a firm to prepare the RFP for a new Civic Center for submission to three competing developer/operator teams. City staff has indicated publicly that it expects the RFP will be ready to submit to the three competing firms by late February 2014 and won't be shown to the Council before it's issued. City staff has also indicated that it aims to bring a recommended developer/operator to a Council vote on July 1, 2014. A new Mayor and Council majority [five new members] will take office on July 15. On Feb. 1, 2014 city staff held a public meeting offering to provide information on the Civic Center project. Mike Conway fielded Q & A. LBREPORT.com asked one of the final questions at the event: LBREPORT.com: ...Can you explain exactly why if the city had materials in its possession since 2005, 06, 07, 08, 09, 10, 11, 12 and 13, that raised seismic issues about City Hall, that it apparently never once put out for an RFP a request for proposals from firms that actually do retrofitting...and instead seems to have created, inferred, extrapolated figures internally from staff, whom we don't vote for, instead of bringing the result of that RFP to the policymaking elected City Council?
blog comments powered by Disqus
Contact us: mail@LBReport.com |
Hardwood Floor Specialists Call (562) 422-2800 or (714) 836-7050 |
Contact us: mail@LBReport.com