LBReport.com

News / Perspective

City Mgm't Says It Doesn't Expect To Bring Council Its Recommendation For Privately Built/Operated New Civic Center Until Roughly September...Likely Concealing Dueling Proposals From Council and Public Until At Least Then


(July 17, 2014, 1:20 p.m.) -- LBREPORT.com has confirmed that city management quietly informed the now-former City Council and former Mayor Bob Foster over two weeks ago that it intends to continue to evaluate through July and possibly as long as the next sixty days what two competing private development/operator teams proposed in a "public private partnership" transaction to finance, build, operate and maintain a new Civic Center.

In a July 3 memo from Director of Business and Property Development Mike Conway to City Manager Pat West for the Mayor and City Council, Mr. Conway acknowledges that two competing proposals were received on June 2 states in pertinent part:

Since June 2, staff and its consultants have spent considerable time in review of the proposals and clarifying certain assumptions in, and conditions to, the proposals. Both proposals are of an incredibly complex nature continue to carefully review and analyze each element of the proposals in detail. Consequently, staff needs additional time to conduct and thorough and exhaustive review of each of the proposals in order to make an informed recommendation. The results of these efforts will contribute toward a determination of responsiveness to the RFP, thereby qualifying the proposer for payment of a stipend and, if appropriate, enable staff to make a recommendation regarding a preferred proposer.

Staff currently anticipates that these discussions will continue through July. Staff is optimistic that a presentation and recommendation can be brought to City Council in the next 60 days.

[Further below, scroll down]






City management's position (if accepted by the new Council) effectively means that neither the new Council nor the new Mayor nor the public will see the responses submitted by the competing developer/operator proposers until roughly September, if then.

In early June, LBREPORT.com sought access to the two proposals under the CA Public Records Act. The City responded that it doesn't release proposals submitted to RFP's until after a contract is signed. LBREPORT.com believes a City Council majority could direct city management to provide access to the submitted proposals under the Public Records Act so taxpayers and decisionmaking Councilmembers could see what's actually proposed before making a decision on the matter. Further to follow from LBREPORT.com on this.

The City paid an outside consulting firm roughly $1 million (voted action by now former Council with Schipske dissenting) to prepare a Request for Proposals directed to three ompeting developer/operators; one dropped out and the two remaining submitted their proposals in response on June 2. The former Council also authorized outside legal counsel fees of up to half a million dollars related to the proposed transaction.

Under the city management-proposed "public private partnership," the City would pay a private developer/operator an annual sum that management says won't exceed current costs plus CPI to finance, build, operate and maintain an entirely new Civic Center complex for roughly 40 years, and would also give the private entity the prime developable land under the former LB courthouse along Ocean Blvd.

The July 3 memo's existence was first reported by veteran PressTelegram reporter Joe Segura online on the evening of July 16. [kudos Mr. Segura.] LBREPORT.com first reported on June 24, 2014 that the July 1 City Council agenda may not include a city staff recommended choice of a developer/operator [and it didn't.]

Under a previously announced timeline, management said it was prepared to bring the Council a preferred proposer for a decisional Council vote on July 1 -- including a vote to enter into a contract -- before Mayor Foster and his former Council majority exited.

As previously reported by LBREPORT,.com, Mr. Conway acknowledged to LB's Harbor Commission on May 12, 2014 that even with what it calls an "aggressive" timeline, a new Civic Center -- whose original justification was to address seismic issues at LB's current City Hall -- wasn't expected to receive entitlements until the end of 2016 or 2017 with construction to follow thereafter. His statement invited the inference [by us] that LB's seismically challenged City Hall might continue in operation through 2017 and possibly into 2018.

City officials first learned of seismic issues at LB's current 1970's era City Hall in 2005 and again in 2007. Critics [including LBREPORT.com editorially] have said that if a seismic retrofit of City Hall had been pursued at that time, seismic work on City Hall might be completed by now.

City management under Mayor Foster (who took office in July 2006) didn't seek bids to determine a marketplace determined cost for a seismic retrofit. Instead, management produced a figure it derived in-house that it presented to the Council and the public on Power Point slides and in city memoranda.



blog comments powered by Disqus

Follow LBReport.com w/

Twitter

RSS

Facebook

Return To Front Page

Contact us: mail@LBReport.com



Need A Plumber, NOW? DrainPros Does It All; Click This Text To See Their Many Services AND Click Below To See Their Current Specials





Click for VIDEO and see how Diversified Threat Management private security can help protect your neighborhood and your business. Affordable group rates available.





Adoptable Furry Family Member








Carter Wood Floors
Hardwood Floor Specialists
Call (562) 422-2800 or (714) 836-7050




Return To Front Page

Contact us: mail@LBReport.com


Copyright © 2014 LBReport.com, LLC. All rights reserved. Terms of Use/Legal policy, click here. Privacy Policy, click here